When the Nanny State Pivoted from Cars to Pouring Concrete: “25 Years On, Hair’s Whiter, But is Anyone Wiser?” 🕰️🤔

MELBOURNE – MAJOR PROJECTS SCORECARD (Transport & Water)

Project Promised Cost / Date Final (or latest) Cost / Date Cost Blow-out Delay Value for Taxpayers Grade Notes (BCR = Benefit Cost Ratio)
CityLink (Stages 1 & 2) $1.8 b / 1999 $2.5 b / 2000 1.4× 1 yr B Concession to Transurban; now seen as positive NPV despite toll hikes.
Western Ring Road (M80) upgrades 2007–2022 $1.9 b / 2012 $3.8 b / 2022 2.0× 3 yrs C Delivered in 5 packages; some sections on time, overall 40 % over.
Regional Rail Link $3.8 b / 2013 $4.3 b / 2016 1.1× 1 yr C Auditor-General: BCR 0.9; patronage 30 % below forecast.
East West Link (cancelled) $6–8 b / 2018 $1.3 b *spent* F $1.3 b spent, zero infrastructure delivered.
Melbourne Metro Tunnel $9 b / 2016 $13.48 b / 2025 1.5× 4 yrs C Auditor-General 2023: revised BCR ~1.2.
West Gate Tunnel $5.5 b / 2022 $10–12 b / 2025 1.8–2.2× 3 yrs C PFAS contamination drove >$3 b blow-out; BCR now <1.0.
Level Crossing Removal (55 sites) $5–6 b / 2022 $8.3 b / 2023 1.4× 1 yr B Program BCR 1.8; delivered 40 % faster per site than historical average.
North East Link $10–15 b / 2027 $26.1 b / 2028 1.7× 1 yr C Business-case BCR 0.7; scope inflation (longer tunnels).
Melbourne Airport Rail $5 b / 2026 $10 b / 2029 (on hold) 2.0× 3 yrs+ F Scope & alignment still changing; not yet contracted.

MELBOURNE – BROAD INFRASTRUCTURE SCORECARD (Buildings)

Project Promised Cost / Finish Final (or latest) Cost / Finish Cost Blow-out Delay Value for Taxpayers Grade Notes (BCR = Benefit Cost Ratio)
Victorian Desalination Plant $3.1 b / 2011 $5.7 b + $18–19 b contract / Dec 2012 6.1× 1 yr F Drought insurance facility; never run at full capacity until 2017; adds $608 m p.a. to water bills even when idle.
Federation Square $135 m / 2000 $450 m / Oct 2002 3.3× 2 yrs B 8 m visitors p.a.; prime civic and cultural asset.
Docklands Redevelopment $7–8 b (1996) $14.6 b / ongoing 1.9× 25 yrs+ D 190 ha renewal; land value uplift >$10 b; criticised for poor public realm.
New Footscray Hospital $1.2 b / 2022 $1.495 b / 2025 1.25× 3 yrs B 504-bed tertiary teaching hospital; first green-star public hospital in Victoria.
Joan Kirner Women’s & Children’s Hospital $200 m / 2021 $220 m / 2023 1.1× 0 yrs A 200-bed women’s & paediatric centre; now state’s 2nd-largest maternity hub.
Australian Institute for Infectious Diseases $300 m / 2025 $400 m / 2026–27 1.3× 1 yr B 10-storey super-lab; pandemic R&D hub next to Melbourne Biomedical Precinct.
Royal Children’s Hospital Redevelopment $1.0 b / 2011 $1.3 b / 2011 1.3× 0 yrs B International award-winning paediatric facility; BCR 2.1 post-opening.
Royal Melbourne Hospital Royal Park $250 m / 2012 $350 m / 2016 1.4× 2 yrs C 200-bed acute tower; emergency dept doubled.
Peter MacCallum Cancer Centre $1.0 b / 2015 $1.2 b / 2016 1.2× 1 yr A Co-located with RMH; integrated oncology hub; BCR 2.4.
Melbourne Convention & Exhibition Centre Stage 2 $205 m / 2018 $235 m / 2018 1.15× 0 yrs B 9 000-seat plenary hall; major events generator.
Melbourne Conservatorium of Music $110 m / 2019 $160 m / 2022 1.45× 2 yrs C University of Melbourne; world-class acoustic halls.
State Library Victoria Vision 2020 $88 m / 2019 $91 m / 2020 1.03× 0 yrs A Heritage-sensitive expansion; 40 % jump in visitation.
Melbourne Arts Precinct Transformation $1.4 b / 2025 $1.8 b / 2025 1.3× 0 yrs B New NGV Contemporary, Arts Centre spire & public realm.
Big Housing Build $5.3 b / 2024 $5.7 b / 2024 1.07× 0 yrs A 12 000 new dwellings; 30 % delivered on budget.